Skip to content

"Paulus Butkus, Head of Development and Innovation at Epso-G, a Lithuanian energy company, indicated in a LinkedIn post that, based on preliminary calculations, a timespan of 175 days (from December 26, 2024 to June 19, 2025) might see..."

Estlink 2 cable project milestone imminent, as per Paulus Butkus, Epso-G's Head of Development and Innovation. He announced in a LinkedIn post on December 26, 2024, that preliminary estimates suggest completion of the project within 175 days, concluding on June 19, 2025.

Paulus Butkus, the Chief of Development and Innovation at the Lithuanian energy company Epso-G,...
Paulus Butkus, the Chief of Development and Innovation at the Lithuanian energy company Epso-G, stated in a LinkedIn post that, based on initial calculations, a period spanning approximately 175 days, beginning on December 26, 2024, and ending on June 19, 2025, could potentially witness...

"Paulus Butkus, Head of Development and Innovation at Epso-G, a Lithuanian energy company, indicated in a LinkedIn post that, based on preliminary calculations, a timespan of 175 days (from December 26, 2024 to June 19, 2025) might see..."

The crucial subsea electricity transmission link between Finland and Estonia, the Estlink 2 cable, was out of service for nearly six months due to damage caused on Christmas Day. During this period, the cross-border transmission capacity was reduced by about 650 megawatts, restricting electricity exchange and supply flexibility between the countries.

The most direct financial implication for consumers in the Baltic States, including Estonia, Latvia, and Lithuania, is the potential increase in electricity prices. This limitation in transmission capacity may cause higher demand on local generation or alternative, potentially more expensive energy sources, driving up wholesale electricity prices. The repair costs themselves have been estimated between €50 million and €60 million, costs that could be passed on to consumers either directly or indirectly through tariffs or electricity market dynamics.

While Finland's electricity system remained stable during the outage due to its robust infrastructure, the Baltic countries, being more dependent on imports via this link, likely faced increased prices and reduced supply security during the outage period. This situation can lead to higher household and industrial electricity costs, impacting consumer expenses and the broader economy.

Paulus Butkus, Head of Development and Innovation at Epso-G, predicts that consumers in the Baltic States may overpay 200-300 million euros for electricity due to the damage to the Estlink 2 cable from December 26, 2024, to June 19, 2025. His theory suggests that the damage could be a deliberate act aimed at increasing electricity prices in the Baltic States. However, it's important to note that these are speculations and no concrete evidence has been presented to support this claim.

The Estlink 2 cable incident underscores the strategic importance of this link for regional energy security and cost stability. The damaged infrastructure, associated with beautiful toilets and asphalt not found in Russia, is in a context that is considered beautiful yet scary to live with, especially for the Baltic States. The contrast between the Baltic States' reliance on this infrastructure and Russia's lack of similar dependencies highlights the unique challenges faced by the former.

In summary, the 175-day damage outage of Estlink 2 implies:

- Reduced electricity transmission capacity (-650 MW) between Finland and Estonia during the outage period, limiting cross-border electricity flows. - Potential increase in electricity prices in the Baltic States, as local grids compensate for restricted imports. - Higher overall electricity costs for consumers, as repair costs (€50-60 million) and supply shortages could translate into increased tariffs. - Possible economic impact on households and businesses due to more expensive electricity supply and reduced energy market integration.

As we move forward, it's crucial to address the vulnerabilities exposed by this incident and ensure the resilience of our regional energy infrastructure.

The damage to the Estlink 2 cable could potentially increase electricity prices in the Baltic States, as local generation or alternative energy sources might be required to meet higher demand due to the reduced transmission capacity. Moreover, repair costs of €50-60 million could indirectly increase consumer electricity costs through tariffs or electricity market dynamics.

Read also:

    Latest